Don Macleod this morning rode the 1700m of North Face trail, end to end non stop.
Initial looking about for this trail was done on October, 2008.
Pilot tracking started in earnest in March, 2009. And 25 or so sessions later…..
The track was given the green light on September 25, 2009.
Work parties started on 15 October 2009, the forecast was for snow..
Since then we have had about 35 work parties and built 14 switchbacks and benched about 1700m of swoopy flowy singletrack.
A very very impressive effort indeed.
***** A huge thankyou to all of those who have helped out :)
Next up, making it as good as it can be.
And, working on the lower section…